NextStar Energy – Utility Connection Work


Utility Connection Work

Design, supply and install all utility piping and electrical at the Next Star Energy EV Battery production site in Windsor Ontario

  • Autodesk Revit 3D modelling
  • ≈ 11,000 meters or piping utility piping (Clean Dry Air, Nitrogen & Potable Cooling Water)
  • ≈ 91,500 meters of cable
  • Installation of busway systems
  • ≈ 80,600 meters of cable tray
  • Interface with 30+ Original Equipment Manufactures (OEM)
  • ≈ 8,346 (1,097 mechanical and 7,267 electrical) connection points
  • Scope spanning over 3 million square feet of the facility
  • Adhering to strict clean room protocols and industrialized zone requirements