NextStar Energy (LG Energy Solutions & Stellantis JV)

NextStar Energy (LG Energy Solutions & Stellantis JV)


Mixer/Coater Line #2 Cathode Piping

Re-design and installation of stainless-steel Mixer and Coater piping at the NextStar Energy EV Battery production site in Windsor, ON

  • Re-design of piping based on the original OEM design, augmented with precision 3D scanning to capture as built to ensure dimensional and routing conformity.
  • ≈ 9,000 meters of ½” to 20” stainless steel piping
  • Stainless steel GTAW and autogenous orbital welding processes
  • Adherence to stringent internal / external pipe cleaning requirements